Freedom, GEABSOLUTE POWERS CORRUPT ABSOLUTELY, General Election (GE15), Malaysia, Politics, polling Nov 19: Destroy Umno for the betterment of Malaysia, race, religion, Solidality, support Aliran for Justice

Share This

Showing posts with label landslide. Show all posts
Showing posts with label landslide. Show all posts

Wednesday 30 May 2018

Penang new Chief Minister taking Penang to the next level

https://youtu.be/mdtJqsLapZU/

Man with a plan: Chow elaborating on his vision for Penang during an interview with The Star at Komtar in George Town.
Man with a plan: Chow elaborating on his vision for Penang during an interview with The Star at Komtar in George Town.   


https://youtu.be/lLfYJvX5ePk

New CM Chow has a clear vision of how to develop the state into the next five years

 

"Economic growth with environmental sustainability would be an ideal situation rather than sacrificing the envoronment for the sake of development - Chow Kon Yeow"


GEORGE TOWN: It’s easy to understand why Chief Minister Chow Kon Yeow is such a popular figure in Penang despite hailing from Kuala Lumpur.

Holding the exco portfolio of Local Government, Traffic Manage­ment and Flood Mitigation for the last two terms here was not an easy task, but Chow’s simple, frugal and austere ways won over the people and even his harshest critics.

Now he is in the hot seat as the chief executive. Here, he shares his thoughts on his plans to move Penang up another notch over the next five years, as well as personal and party matters. Below is an excerpt from the Q&A:

How are you keeping after more than two weeks into the top post in Penang?

It’s a continuation of where I left off for 10 years as a state executive councillor in 2008. At the Chief Minister’s office, I deal with a wider range of issues than my portfolios under Local Govern­ment, Traffic Management and Flood Mitigation, which were more focused.

As Chief Minister, I also have to look into investment and economic issues, besides being chairman of Penang Development Corporation, PBA Holdings Bhd and other state statutory bodies.

Which plans do you intend to see through in your first term?

Upon taking office on May 14, I took up the Transport portfolio because I intend to see to the implementation of at least some of the projects under the Penang Trans­port Master Plan (PTMP). It is too ambitious to say that we will implement all the projects, but they will be a priority.

On the projects by Consortium Zenith Construction Sdn Bhd (CZC) comprising the RM6.43bil undersea tunnel and three paired roads, we will likely begin construction for one of the three major roads.

As for SRS Consortium, the project delivery partner of PTMP, we will start the Light Rail Transit (LRT) project. Since it is tied to Penang South Reclamation (PSR) in the southern coast of Penang island, the reclamation of three man-made islands will have to start as well to finance the LRT project.

(The PSR is a massive plan to reclaim three islands totalling 1,800ha off the southern coast of Penang island. The success of PTMP, the state government’s multi-billion ringgit public transport project involving LRT, monorail, cable cars and water taxis, depends on funding from property development on the islands.)

One important element here is that people see the reclamation as solely financing the infrastructure projects, which is true in a sense. The man-made islands will not only finance the infrastructure projects, but the lands made available will help meet the development needs of Penang for the next 30 years.

It is near to the Bayan Lepas industrial electronic and electrical cluster. Taking it away from the cluster will not produce the synergy effect.

And preferably, the expansion of our industrial zone into the future must also be near to the cluster and Penang International Airport facilities.

So we can safely say that the three man-made islands are a sure thing?So we can safely say that the three man-made islands are a sure thing? /b>

It is subject to review by the Federal Government. We need approval from the Federal Govern­ment for any large-scale project and the reclamation is one of them. It has to be approved by the National Physical Planning Council. If we can get all the necessary reports to support our application, it will be tabled at the National Physical Planning Council for approval.

You said the LRT component of PTMP is your priority. When can we expect to see it materialise?

We have made a submission to the Land Public Transport Commis­sion (SPAD) since March 2016 for a railway scheme.

Besides the LRT line from Komtar to Bayan Lepas, we have also submitted the other alignment as a full package, as our depot will be built on one of the man-made islands that has yet to be reclaimed. We are still waiting for the environment impact assessment approval.

I believe our application is still active. Hopefully, it will be brought before the Transport Ministry for deliberation and approval.

Previously, it was either an undersea tunnel or a third bridge to link Bagan Ajam and Gurney Drive. What will it be now? It is still too early to say. We can always make changes because of the cost factor. There is no firm decision on this. CZC will have to complete the feasibility studies first, which are now at 96%.

There is no hurry because even if we were to build the undersea tunnel, it would only take off in 2023.

Right now, CZC’s priority is to start building the 5.7km paired roads starting from Jalan Kampung Pisang in Ayer Itam and connecting with the Tun Dr Lim Chong Eu Express­way in Gelugor. It is one of the three major roads undertaken by CZC.

What are your thoughts on the claims that CZC paid RM22mil to cover up anti-graft investigations on the mega project comprising the undersea tunnel and three paired roads?

It is entirely up to the Malaysian Anti-Corruption Commission to investigate, as it has nothing to do with the state government. We are not the approving authorities.

The concession companies ap­pointed by us are responsible for getting all the approval. What CZC told us was that it was basically political extortion. They were under great duress and had no choice but to believe that the other party could help smooth the process of getting the necessary approval.

This had nothing to do with the state government and we had no prior knowledge of it until it was reported in the media.

Penangites have been plagued by floods on some occasions. What are your plans to resolve this?

The first phase of Sungai Pinang Flood Mitigation project was completed in the late ‘90s and it never went beyond that. This project has been delayed for 18 years.

We need about RM600mil to resolve the problem. The money can be used to build a barrage along the river near the People’s Housing Project in Sungai Pinang. If there is a barrage, backflow from the sea during high tide would not flow inland.

Other components include the construction of pump houses, retention ponds, collector drains along the river, deepening of rivers and the raising of bunds. All these measures are expected to be completed in three and a half years.

We believe these measures will help mitigate floods. All designs can only cater to a certain capacity, so we cannot say that there will be no floods after this.

It is important to secure approval and funding from the Federal Gov­ernment. The Sungai Pinang Flood Mitigation project is vital because it has impact upstream, as there are six tributaries linked to Sungai Pinang.

Many hillslope developments have taken shape, especially in the Tanjung Bungah area, which has drawn concern from environmental activists. What is your take on this?

The current state government will not change the tight guideline of restricting development 76m or 250ft above sea level, although the national guideline can go up to 500ft. The guideline is very restrictive as it will prevent a lot of hill lands from being developed.

This guideline only came into place under the Penang Structure Plan approved in 2007. Before that, approval had already been given to certain developments we can’t stop abruptly. Under this category, there are many projects approved that went beyond the restriction.

I will get the Penang Island City Council to brief me on how much land is still left that is restricted by the guideline. If there is not much land left, we will consider that the guideline will prohibit hillside deve­lopment in the future.

If the guideline is still in place, the people of Penang must confront the fact that there won’t be any development beyond this guideline. Land will become expensive. If there is no reclamation, what will the future hold for Penang island?

Gentrification is an issue in George Town, with foreigners snapping up properties within the Heritage zone. What do you think of this?

Prior to interest in our heritage buildings and before the inscription of the Unesco World Heritage Site, there were a few hundred houses in need of refurbishment. Some houses collapsed during storms.

If you look at the heritage site today, there are few dilapidated houses left due to the interest in heritage properties. The owners have greater appreciation of their value.

My personal stance is to save the house first. If there are buyers, we should save the buildings and negotiate on their use later.

The Opposition in Penang is down to only three representatives – two from Umno and one from PAS. Will they be given any allocation?

They will be given allocation, although the figure may not be the same as the Government’s assemblymen. They rejected it last time, thinking that we were setting a trap on them.

Previously we offered them RM40,000 in annual allocation, but it will be more this time. The funds can be used to support the community, as well as assist organisations in their work and in getting facilities such as fax machines. The funds are meant for the people.

The Opposition is weak in the state assembly. How do you view this matter?

In a healthy Western democracy, when there is a weak Opposition, backbenchers play a more active role in scrutinising government policy. It is a working mechanism. A new check-and-balance in the ruling coalition can emerge to play this role of checking the executives and government on the use of public funds and policy.

Regarding tourism, is there any new programme that your administration would like to introduce to attract visitors within the next five years?

We should be more selective not only in terms of quantity matters, but in terms of quality as well. We need to have niche tourism markets to get high spenders.

At the moment, we cannot be choosy as we need them to fill up our hotel rooms and patronise our local businesses. But there will come a time when it will negatively impact the local environment.

We should move up a notch by focusing on higher spending and business travellers rather than the usual travellers.

In your own opinion, what should an ideal Penang look like?

Economic growth with environmental sustainability would be an ideal situation rather than sacrificing the environment for the sake of development.

Development has to be balanced not only geographically, but also in the strata of society, meaning that the B40 class (households earning RM3,900 a month or less) must be able to benefit from the economic development.

There must be job opportunities and stable income for them. They must not be sidelined or living in poverty without jobs. If jobs can be made available to foreign workers, why can’t it be the same for locals?

You won the Pengkalan Kota state seat in 1990, but lost it in 1995. What was it like having to start from square one?

I was back to full-time party work in 1998 to lead the party after the “Knock Out Kit Siang” internal party strife. After 1999, I was picked as state DAP chairman to continue the party’s struggle in Penang.

What was it like being a DAP-elected representative before and after 2008?

Very different. The government representatives have more resources to serve the people better. But we keep instilling the idealism of our party struggle and the long-term vision to win Federal power into our representatives so that they see a bigger vision for the party and themselves.

Many Penang DAP leaders are now in their 60s. Has the state party leadership identified the next echelon of leaders?

The party made a bold decision by fielding many new candidates in the 14th General Election. They have potential for future development in the Government and party. This is a rejuvenation process to prepare them for the future.

Source: The Star by alex tengtan sin chow

Related:

CM: Transport plan components will be fully funded - Metro ... 

 

Rude awakening for storm victims - Metro News - Penang fresh flood again

 

All riled up over slow response - Metro News 

 

Huge landslide in Tg Bungah hill 

 

To Malaysia with love, from the world

Friday 25 May 2018

Huge landslide in Tg Bungah hill

Disaster zone: An aerial view of the recent landslide in Tanjung Bungah, Penang.
An aerial view of the brown water flowing into the sea from Sungai Kelian.


GEORGE TOWN: Nobody knew a natural disaster was waiting to happen until Sungai Kelian in Tanjung Bungah turned brown and silty.

The sudden profusion of laterite mud flowing out to sea was caused by a landslide even bigger than the one that killed 11 people at a Tanjung Bungah construction site last year.

But it was so far uphill – 231m above sea level – that Penang Island City Council (MBPP) had to use a drone to find it.

As it was a natural landslide, residents are now worried about the fragility of slopes in the Tanjung Bungah hill range and want tighter scrutiny on the many development projects slated for their neighbourhood all the way to Batu Ferringhi.


MBPP issued a statement on Sunday after discovering the landslide on Bukit Batu Ferringhi, in the forest reserve about 1.5km uphill of a disused Penang Water Supply Corporation (PBAPP) intake station.

PBAPP chief executive officer Datuk Jaseni Maidinsa clarified that the station had not been in use since 1999, after the Teluk Bahang Dam was completed.

An MBPP engineer said the landslide was about 40m long and 20m wide, but geo-technical experts were unable to reach the site to determine what happened because there are no jungle trails to reach it.

A group called Nelayan Tanjung Tokong shared a video on Facebook last Thursday, showing the russet brown water flowing into the sea from Sungai Kelian and expressed concern.

Tanjung Bungah Residents Asso­ciation chairman Meenakshi Ra­­man said it was worrying because the landslide happened without any human disturbance.

“It shows the hills in the vicinity are ecologically fragile, and we don’t want any untoward incidents to happen again.

“We hope the authorities will tell us what is being done to prevent further landslides,” she said yesterday.

Former Tanjung Bungah assemblyman Teh Yee Cheu said he knew the area well and believed that the landslide took place near the source of Sungai Kelian.

“I have always stressed on how sensitive the hill slopes here are. There are many underground springs in the hills,” he said.

State Works, Utilities and Flood Mitigation Committee chairman Zairil Khir Johari said the landslide happened in the middle of a forest reserve and experts need time to study the slope to understand how it gave way.

He gave an assurance that the mud washing down the river would clear up in due course without long-term damage.

Zairil also stressed that no deve­lopment had been approved near the landslide area.

“The state government’s guidelines on hill slope development are tighter than those used by the Federal Government. We will not approve developments without pro­per compliance,” he added.

Penang Drainage and Irrigation Department director Mohd Azmin Hussin said that it would be difficult to transport machinery to the source of the landslide for mitigation works.

“There are no access roads and the team will have to hike to the site,” he said. - The Star

Related posts:

Don’t allow another landslide tragedy to happen !


NGO draws up own manifesto to assist the next state government  (From left) Anil, Ben, Dr Chee, Khoo Salma, Dr Anwar and Dr Ka...
Halt all hillslope development, Penang Forum tells state | Free ... FMT - GEORGE TOWN: The Penang Forum has repeated its call for al..

Friday 26 January 2018

Penang Landslide occured days after remedial works started

Cracks at Tanjung Bungah site began in June, Commissioner of Inquiry told


Expert panel: (From right) Yeo, Dr Gue and Prof Ramli arriving for the inquiry.
 
GEORGE TOWN: A temporary structure supporting a worksite slope in Tanjung Bungah developed cracks in mid-June, a Commissioner of Inquiry heard.

Soil Mechanic Sdn Bhd director Cheah Wing How, who was a sub-contractor of the project where a landslide killed 11 workers, said he was informed by a clerk to carry out remedial works as the granite wall had cracked.

Cheah said his team left after completing the granite works and soil-nailing works to enhance the stability of the temporary slope.

There was, however, no mention when they completed the works.

“When we returned, we found there were pile cap excavation works carried out near the slope.

“We believe there was soil movement that resulted in the cracks on the granite wall.

“We were carrying out remedial works and 11 days into the job, the landslide happened,” said Cheah, who has 20 years’ experience in the field.

Cheah was testifying on the first day of the public hearing into the landslide tragedy by the State Commission of Inquiry (SCI) at City Hall in Esplanade yesterday.

On Oct 21, last year, a landslide hit the affordable condominium project made up of two 49-storey towers with 980 units in total within the Permai Village township near the Tunku Abdul Rahman University College.

Among the 11 killed was site supervisor Yuan Kuok Wern, 27.

During the proceeding, the Penang Island City Council (MBPP) also presented eight drone videos that showed the slope and the surrounding area after the tragic incident.

SCI chairman Datuk Yeo Yong Poh said they planned to carry out a site visit tomorrow.

He also fixed the hearing to continue until Monday, followed by Feb 8 to Feb 11, March 24 to March 28 and April 18 to 25.

Other members of the commission are geotechnical expert Datuk Dr Gue See Sew and forensic geo-technical engineer from Universiti Teknologi Malaysia Prof Ramli Nazir.

The SCI was gazetted on Dec 21 last year to investigate the landslide after Yang di-Pertua Negri Tun Rahman Abbas gave his consent on Dec 6, 2017, for the appointment of the members of the commission and its terms of reference.

Meanwhile, Penang Citizens Awareness Chant Group (Chant) adviser Yan Lee said the entrance to the Teik Granite Quarry, which is located near the site where the landslide occurred, should be fenced up.

“Anyone can just walk into the site as the safety measure is not up to mark.

“We have voiced our concern to the Penang Island City Council, the Department of Environment as well as the Land and Mines Department,” he said yesterday.

By Chong Kah Yuan and Jo-Leen Wong The Star

Related Links:

Contractors in jitters over temporary slopes - Nation

 

Boulders slid down hill prior to disaster - Nation





Related posts:

Penang landslide tragedy, plea went unheeded, no one listened !

 

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'..

Thursday 26 October 2017

Penang Paya Terubong Residents living under shadow of fear!

Put on hold: A view of the site for the development of four apartment buildings in Paya Terubong, Air Itam.

GEORGE TOWN: Since the deadly landslide in Tanjung Bungah, people in Paya Terubong are looking over their shoulder – and up at a nearby hill.

They have been trying for years to stop a project comprising four towers, each over 40 storeys tall, approved on a hillside across the road from their homes.

Because the project has already been approved, the residents are down to one last resort – the state Planning Appeals Board.

“We must try. The only thing between our homes and those four towers will be a new two-way street that the developer will build if this project goes on,” said Taman Sri Rambai and Taman Lau Geok Swee Residents’ Association chairman Dr Ti Lian Geh.

The plan, he said, was supposed to be six-storey townhouses but the developer put in a request to change it to high-density apartments.

He said the residents have been living in fear after learning that the development plan was changed to three blocks of 47-storey luxury apartments and a 41-storey block of affordable housing.

He said a hearing is ongoing with the Planning Appeals Board to stop the development.

“Building skyscrapers on a steep hillslope is dangerous. If the towers come down, the whole neighbourhood will be gone,” he said, adding that the high-density project will also worsen traffic congestion there.

He told a press conference yesterday that the earthworks two years ago caused frequent flash floods, mudslides and torrential mudflows in the neighbourhood.

Penang MCA and Gerakan, which organised the press conference, urged the state government to revoke the approval.

Bukit Gelugor MCA division deputy secretary Choong Jun Jie said that every time there is a downpour, the residents worry.

“We do not want another tragedy,” he said.

Penang Gerakan vice-chairman Oh Tong Keong said people’s lives are in jeopardy when highrise projects are given priority.

The staggered hillslope is now covered with geotextile sheets after the Penang Island City Council issued a stop-work order about two years ago.

Penang Island City Council Engineering Department director Addnan Mohd Razali said all construction work there except for mitigation measures have been stopped pending the outcome of the residents’ appeal.

Source: The Star by Logeiswary Thevadass and Rena Lim

Related Links:


Compensation sought for landslide victims’ families

Sadness turns to anger as the blame game hots up


Related posts:


https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff...



Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ...



Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'..


https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s.



Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood...



Humans Are Destroying the Environment   PETALING JAYA: They are supposed to be guardians of the environment, and yet “certain enforcem..

Errant hill clearing by developers causes of floods, sinkholes, seepages damaged houses!

 

Save Penang Hill from the greedy

 

Penang Forum concerns over hill clearing and floods; the Declaration & Recommendation

 

Getting titles right in the engineering field in Malaysia

   Getting titles right in the engineering field in Malaysia ..

RECENTLY, the Institution of Engineers Malaysia (IEM) received an enquiry on the usage of the title “Engr.” for members of the institution. The title “Ir” was first introduced by IEM in the early 1970s for both the graduate and corporate members of the Inst...Getting titles right in the engineering field in Malaysia rightwaystosuccess.blogspot.com

Penang landslide, whose faults?



https://youtu.be/4qaOB1n5tgA

GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the affordable housing project that was hit by a landslide in Tanjung Bungah on Saturday, claiming the lives of 11 workers.

This is because the state government wants the matter investigated and the responsible parties to be charged, state Local Government Committee chairman Chow Kon Yeow said.

He stressed that the incident was a construction site accident.

“We hope the council and other related agencies will give their fullest cooperation to the police,” he told a press conference at Komtar yesterday.

At the same conference, Mayor Datuk Maimunah Mohd Sharif acknowledged that the project was rejected by the Department of Environment (DOE) but said it was approved by the state because it complied with Penang’s Safety Guidelines for Hill Site Development 2012.

Besides, she said, the DOE had approved a residential project and a private education institution that were even closer to the quarry.

“It is located more than 500m from the quarry’s blasting point while federal guidelines only require a minimum distance of 350m.

“The project’s site is zoned as ‘general residential’ and the slope gradient is less than 20°.

What a mess: Some groups believe that if the DOE’s advice had been heeded, the landslide tragedy could have been avoided. — Bernama

“The land is also less than 76m above sea level with the site located on a contour between 18m and 40m,” she said.

Maimunah said that based on all the requirements, the council’s One-Stop Centre (OSC) – which comprises members from more than 20 technical agencies at state and federal level – agreed to approve the project.

The OSC is in charge of approving property development plans on the island.

“The earthworks planning permission was presented to the OSC on May 14, 2015, and it was approved with conditions on June 6, 2015, while the commencement of work approval was given on Jan 18 last year,” she said.

However, the Tanjung Bungah Residents Association was not happy with the reasons given by the council for allowing the project.

“How could the council ignore the advice when the DOE is the authority responsible for protecting the environment?” association chairman Meenakshi Raman asked.

Penang Island City Council mayor Datuk Maimunah Mohd Sharif telling a press conference that the project met state guidelines.
 “If they had heeded the DOE’s advice, this tragedy could have been avoided and lives would not have been lost.”

“We feel betrayed ... the state government failed to listen to us,” she said yesterday, commenting on Maimunah’s statements at the press conference.

Penang Federal Action Council chairman Datuk Seri Zainal Abidin Osman urged the state government to immediately set up an independent body to audit all approvals of hillslope development projects made by the various state authorities.

“The Penang government has to take responsibility and be accountable for the tragedy involving the loss of 11 lives.

“We ask it to stop blaming others for any accident which occurred since it became the state government.

“We are surprised that a project which was not supported by a technical department was still given approval by the state authority,” he said in a statement.


An undertaker (in white) and a priest performing prayers at the scene of the landslide for site supervisor Yuan Kuok Wern, 27, who was killed in the tragedy.


The Institution of Engineers Malaysia (IEM) also came forward to offer technical assistance and opinions in the investigation.

Its president Dr Tan Yean Chin said in a statement that IEM is recognised locally and internationally as a professional body representing a wide cross-section of the engineering practice.

“As a learned society with over 40,000 members and affiliated to several international engineering organisations, IEM is able to offer expert opinions on this tragic event,” he said.

Source: The Starby lo tern chern, logeiswary thevadass, cavina lim, crystal chiam shiying, r. sekaran, rahmah ghazali, danial albakri



Related Links:

No request for an EIA, says Lim - Nation


https://youtu.be/uQjUiwLxD8o

Penang govt told off for not properly responding to tragedy - Nation ...

Penang govt asked to submit report - Nation | The Star Online

Penang govt to blame for the Tanjung Bungah landslide? | Free ...

Two Penang political parties lodge police report on Tanjung Bungah landslide

Tg Bungah tragedy: Let state inquiry commission do its work

Penang mayor defends approval of housing project despite DOE ...

Penang landslide: Engineers must also ensure safety, says IEM | Free ...

Developer: Unbiased probe into cause - Nation | The Star Online

SCI to probe Penang tragedy from five angles - Nation



SCI getting off on a wrong footing - Nation

The right way: Tang (right) and Penang MCA Public Services and Complaints Bureau deputy chief Tan Eng Hin explaining what really should have been done to conduct a fair inquiry at the MCA headquarters in Penang.

Wait for SCI findings - theSundaily

Boiling over landslide tragedy
Group: Not enough engineers to monitor hillside projects
American couple recall workers’ harsh plight
Penang govt asked to submit report
Supervisor’s family to cremate his remains
Everything happened so fast, says site worker
DAP MP pens poem about interfering with nature

Residents' Association Surprised State Govt Allowed Housing Project



Penang City council to instal flood sensors to warn relevant authorities

 

 

Related posts: 

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'...

Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ...

https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s..



Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood...


Structural defects to blame, stop history repeating itself !




 

Getting titles right in the engineering field in Malaysia

  Getting titles right in the engineering field in Malaysia ..

RECENTLY, the Institution of Engineers Malaysia (IEM) received an enquiry on the usage of the title “Engr.” for members of the institution. The title “Ir” was first introduced by IEM in the early 1970s for both the graduate and corporate members of the Inst...Getting titles right in the engineering field in Malaysia rightwaystosuccess.blogspot.com


Penang landslide tragedy, why it happened?

Speaking out: Penang Forum members protesting outside the CAP office in George Town.

Don’t just make it about worker safety issues


https://youtu.be/xVK77MvxrZw


GEORGE TOWN: A Penang Forum member is worried that the state’s proposed inquiry into the Tanjung Bungah landslide will only focus on worker safety issues.

Meenakshi Raman, who is also Tanjung Bungah Residents Associa­tion chairman, said the inquiry should instead look at the laws that have not been followed and whether or not the Penang Structure Plan (PSP) was neglected.

“It should also look at whether the Penang Island City Council (MBPP), which has the authority to act, failed to properly do its job.

“We hope the commission will broaden its scope of inquiry,” she told press conference at the Consu­mers Association of Penang (CAP) office yesterday.

Penang Forum is a loose coalition of several civil society groups in the state.

The coalition, which includes Sahabat Alam Malaysia, CAP, Malay­sian Nature Society, Women's Centre for Change, Penang Heritage Trust, Friends of Botanical Gardens, and 25 residents’ associations and management committees, urged the state to halt all hillslope projects immediately.

It also wants the state to amend the 2009 guidelines on “special projects” to explicitly prohibit development on hill lands except for essential public services.

Forum member Dr Lim Mah Hui said the Penang Hills Watch citizens’ initiative provided the state government with information on hill cutting it collected from the public.

“In January, this site was the first case we highlighted to the state government.

“Photos of construction and hill cutting there were presented to the state government. It responded that the ‘earthwork is being monitored’,” he said.

Dr Lim said Chief Minister Lim Guan Eng wrote in the Safety Guidelines for Hillside Development in 2012 that local governments were to strengthen their geotechnical units, which process and approve applications for hillside developments, and follow up with strict enforcement.

“It says a monitoring team will be established to ensure compliance in construction and performance (of projects).

“The question is what happened then? Did the state and local governments follow their own guidelines? Or was there gross negligence?

“Such a tragedy could have been avoided,” Dr Lim claimed.

He also said parties like the State Planning Committee, MBPP’s One-Stop-Centre Committee (which approved the project), the engineers, the developer and contractors should be investigated.

CAP vice-president Mohideen Abdul Kader said Penangites’ concerns over hill development dated back some three decades.

“Remember the proposed Penang Hill development which we managed to cancel in the end? What the state must do now is look after the natural resources and listen to the NGOs.

“Public pressure can make a difference,” he said.

Another forum member, Dr Kam Suan Pheng, said the Penang Structure Plan forbade development on hill land 76m (250ft) above sea level or with a gradient of 25° and above.

“But many developers cut hillslopes, making them steeper and less stable.

“The weather is always blamed but there was no rain for the past week. So how did the landslide happen?” she asked.

Dr Kam said the Safety Guidelines for Hillside Development clearly state that “if you have a slope ... depending on the height of the slope, you need to have a buffer zone that is greater than the height of the slope.”

“From the media reports, the height of the affected slope is 10m, so there should be a buffer zone of 10m from the foothill,” she said, adding that the inquiry should explore this aspect.

Penang Citizens Awareness Chant Group adviser Yan Lee urged the developer to conduct studies on improving on-site safety measures and engage foreign consultants to make sure the project can go on safely.

“They should also make sure the deceased workers’ families are taken care of.”


Related posts:



https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s...



Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'...


Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ...

https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff...

Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood...


Getting titles right in the engineering field in MalaysiaGetting titles right in the engineering field in Malaysia ..

RECENTLY, the Institution of Engineers Malaysia (IEM) received an enquiry on the usage of the title “Engr.” for members of the institution. The title “Ir” was first introduced by IEM in the early 1970s for both the graduate and corporate members of the Inst...Getting titles right in the engineering field in Malaysia rightwaystosuccess.blogspot.com


Related Links:

'DOE rejected developer's application ...

Penang government urged to halt all hillslope project